Thursday, May 28, 2009
One Ski Hill Place Update
Construction progress continues at One Ski Hill Place as the crews are enjoying the warmer weather! The latest updates from the field are the following:
* Structural steel for the entire building is substantially complete.
* Fireproofing is nearing completion for Levels 1 and 2 and work on Level 3 has started.
* Roof sheeting, which is the metal base structure of the roof, is coming to completion.
*Concrete slab on the metal deck (flooring structure and base) has begun on Level 4
April 29: "Topping Off." A milestone moment! The last large remaining pieces of structural steel, the cupola, was placed on top of the building.
May 16: "Blue board" or siding panels start to be installed on the lower levels.
May 19: Steel roof sheeting is nearing completion on the building near the furture Apres Ski Bar.
Estimated completion is Spring 2010.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment