Construction progress continues at One Ski Hill Place as the crews are enjoying the warmer weather! The latest updates from the field are the following:
* Structural steel for the entire building is substantially complete.
* Fireproofing is nearing completion for Levels 1 and 2 and work on Level 3 has started.
* Roof sheeting, which is the metal base structure of the roof, is coming to completion.
*Concrete slab on the metal deck (flooring structure and base) has begun on Level 4
April 29: "Topping Off." A milestone moment! The last large remaining pieces of structural steel, the cupola, was placed on top of the building.
May 16: "Blue board" or siding panels start to be installed on the lower levels.
May 19: Steel roof sheeting is nearing completion on the building near the furture Apres Ski Bar.
Estimated completion is Spring 2010.